NTDC installs shunt reactors on Dadu-Jamshoro transmission line

May 11, 2021
Misc
Posted by Patrick Haddad

Pakistan’s National Transmission Despatch Company Limited (NTDC) has installed 3×22 MVAR shunt reactors on 152 kilometers long 500 kV Dadu-Jamshoro transmission line emanating from 500 kV Dadu Grid Station.

The shunt reactors have been energised with an estimated cost of around $2.2 million.

The smooth power supply will be ensured to the consumers of Sindh through the Power Distribution Company (Disco). Shunt reactors are used in high voltage energy transmission systems to control the voltage during load variations.

A spokesman said the NTDC is vigorously pursuing its ongoing projects for early completion. Recently, the company has also completed four more 500 kV transmission line circuits for the evacuation of electricity from power plants located in southern parts of the country.

The transmission line circuits have been connected with HVDC Converter Station at Matiari. Moreover, up-gradation work of 130 km long 220 kV Jamshoro-KDA transmission line was also completed before its deadline.

The transmission line is transmitting 450MW additional power from National Grid to K-Electric.

Source: Pakistan Today

Photo (for illustrative purposes): Energetics / Pixabay / free for commercial use